Thursday, February 3
General Notes
- Please do not pick up issues tagged with needs-design until the tag has been removed.
- MMOTD: Merov
- Please remember to move issues to current Sprint when a) starting work on them or b) accepting issues from the community
Team Status
Merov Linden
PAST
- More SNOW triaging: only a dozen left to go...
- Merge Monkeying: push fixes in both viewer-beta and viewer-development, PO build
- STORM-864 : APR memory pool : finished code review, did a test build, plenty of issues. Rejected review. See JIRA for details.
FUTURE
- MM
- STORM-864 : APR memory pool : waiting on Aleric, suspecting some apr bundling issues on Linux and Windows
- STORM-955 : Massively duplicated objects : keep an eyes on this
- STORM-746 : KDU Improvements: Compress j2c with precincts
IMPEDIMENTS
- none
Oz Linden
PAST
- Created 'Open Development' jira project
- Non-Snowstorm activities
- Started discussions about open data APIs
FUTURE
- Review autobuild changes from NickyP
- Document policies and test new jira project rules
- PO Review
- Internal Linden training session
IMPEDIMENTS
- none
Q Linden
PAST
- STORM-465
- Triage tooling attempt (which sadly failed, but i have ideas)
- OOO / Doctor
- beta 3
FUTURE
- beta 3
- internal training session
- OOO late today and all day tomorrow
- spend time with wolf but probably not 'til monday
IMPEDIMENTS
- none, other than time
Grumpity ProductEngine
PAST
- prep for product tirage
- a bit more jira cleanup
- non-snowstorm stuff
FUTURE
- PEQA deferred issues triage with Bambers
- continue to prod others to resolve impediments
- STORM-379, STORM-465
IMPEDIMENTS
- we need more vwr triage - bug queue is getting empty
Paul ProductEngine
PAST
- BUG STORM-680 (Avaline callers are added to the Recent list)
- WIP. 90%. Estimate 2 hours. Implementing the solution.
FUTURE
- Finish with BUG STORM-680 (Avaline callers are added to the Recent list)
IMPEDIMENTS
- Today's progress is not very good because of headache. Today will go home a little bit earlier, feel bad.
Seth Productengine
PAST
- BUG (STORM-433) Friendship offer shifted up and placed over "Second Life" text
- Found that reshaping text editor with a friendship offer fixes its placement. Still looking for more precise reason of the problem
FUTURE
- BUG (STORM-433) Friendship offer shifted up and placed over "Second Life" text
- Estimated: 8-10 hours.
IMPEDIMENTS
- BUG (STORM-379) Content permissions aren't refreshed in the "Buy copy of" floater.
- Asked in JIRA whether the bug should be fixed in a way that may increase server load.
Vadim Productengine
PAST
- Looked through high impact issues (in code familiar to me) from the recent Coverity report.
- Haven't found anything dangerous (and even if I had found something, I don't know the process to handle such issues).
- Story STORM-2 (Customizable viewer layouts):
- Working on saving sidebar state. Stuck with handling minimization.
- I remember Andrew mentioning a bug in LLFloaterReg which may cause it to misbehave. Will try consulting with him tomorrow.
FUTURE
- Will work on STORM-2 at least till the end of week.
IMPEDIMENTS
- none
Andrey ProductEngine
PAST
- picked up Beta3 build#2 (r220251)
- executed smoke and integrity tests on Windows, Linux and OSX. See IQA-80 for more details.
- smoke on Linux has been failed but it looks like specific environment issue (?)
- proceeded with v-d regression testing, see spreadsheet
- reported 2 issues: VWR-24714 and VWR-24715
FUTURE
- investigate VWR-24714
- verify integrated STORM tickets against the latest v-d build FUTURE
IMPEDIMENTS
- none
Wolfpup Lowenhar
PAST
- Worked @ RL .
- STORM-236 : began debuging issue with button layout resized issues. Also discussed this with Oz in IRC.
FUTURE
- Work @ RL
- STORM-941 : email Oz and Leyla concering posible areas that could be causeing the problem.
IMPEDIMENTS
- STORM-236 : waiting for new graphics and name to call the panel.
- Not enough time to actually work on code.
- Computer repair Client that dose not know what non repairable means and keeps trying to have me fix a unit that is beyond repair.
Jonathan Yap
PAST
- VWR-24628 (Descriptive text missing next to first checkbox in About Land/Access)
- This had to be fixed first in order to work on Storm - 953. 4 other people helped with this! This was my proudest moment as a developer. Great team effort. Easy fix but caused by low-level routine change.
- STORM-953 (Clarify what happens when you uncheck Allow Public Access)
- Needs a very quick design review. See image attached to jira https://jira.secondlife.com/secure/attachment/47772/AboutLandNote.png
FUTURE
IMPEDIMENTS
- VWR - 24628 needs to be pulled in to Storm-nnnn
- Waiting for Oz to Storm-nnnn-ize my bug list.
Cummere Mayo
PAST
- jira stuff
- lots of office hours
- getting in trouble ><
- testing correct po build
FUTURE
- new blog posts
- not totally sure
IMPEDIMENTS
- time