Snowstorm Daily Scrum Archive
Friday, September 3, 2010
General Notes
- Don't forget to grab tasks from the Sprint Backlog and update your time remaining on that task each day!
- Merge Monkey of the Day: Merov
Team Status
Aimee
PAST
- "As a developer, I would like to clean up the way the voice code shuts down, so that it doesn't leak memory and satifies my OCD".
- Work out what's gone wrong with the hg convert process on james/viewer-identity-evolution
- Hairy merge of james/viewer-identity-evolution with dessie/viewer-public to fix it.
FUTURE
- Continue hairy merge of james/viewer-identity-evolution with dessie/viewer-public and hg convert.
IMPEDIMENTS
- Will need a yes/no to integrate from design review of VWR-21253 before I can move onto that task, other stuff I can do for now though.
Tofu
OOO
Oz
PAST
- Sent code review system request to systems team
- Prepped discussion of upcoming common code split
FUTURE
- Post first Development build on secondlife.com ?
IMPEDIMENTS
- none not planned for
Merov
PAST
- VWR-22761 : LLKDU upgrade:
- Perf data instrumentation: created baseline using LLFastTimer but not enough info in there. Need to improve that system or go for a quick and dirty hack...
- Created forked repos for indra-private and discussed with Alain. Newest Alain's code though doesn't build :(
- Created forked merov_linden/viewer-development-vwr-22761 for this feature ('cause I'm gonna touch lots of things...)
- Merge monkey: nothing to do 'cause Tofu stole all my toys...
- Snowglobe OH
FUTURE
- VWR-22761 : LLKDU upgrade: Modify LLFastTimer to allow "datasize" in and out tracking
IMPEDIMENTS
- Kakadu license upgrade
Q
OOO
Esbee
PAST
- Out half day yesterday
- Great interview with Dusan Writer
- Met about Jira triage
- Started documenting how Jira VWR triage will work
FUTURE
- Follow up on VWR-21253
- Respond to Resident Viewer ideas
- Groom backlog
- Finish blog post about Product and Snowstorm
- Edit Q's blog post
IMPEDIMENTS
- None
Paul
PAST
- TASK VWR-21585 (Make all tabs support horizontal resizing)
- In progress. Estimate ~ 20 hours.
FUTURE
- TASK VWR-21585 (Make all tabs support horizontal resizing)
IMPEDIMENTS
- none
Andrew
PAST
- Task VWR-20702 (Bottom bar button reordering):
- Sub-task VWR-20705 (Drag&Drop implementation): Done, will commit shortly.
- Sub-task VWR-20706 (Make sure auto-hiding and shrinking buttons still work): Done, will commit shortly.
- Sub-task VWR-22690(Saving/restoring button order). Investigated. Estimate: 5 hours.
FUTURE
- Finish and send for review VWR-20705 (Drag & Drop implementation) and VWR-20706 (Make sure auto-hiding and shrinking buttons still work).
- VWR-22690 (Saving/restoring button order).
IMPEDIMENTS
- none
Vadim
PAST
- Task VWR-21127 (Implement saving size and position of detached tabs): Done.
FUTURE
- Help Paul with VWR-21585, approve integrating the whole feature (although most was done today by Tofu)
IMPEDIMENTS
- none
Sergey
PAST
- Task (VWR-21060) Fix broken ability to open a side tray tab via shortcut, menu item or button outside of the Side Tray.
- Completed. But later found more bugs, fixing them now.
- Task (VWR-20696) Write code to allow for undocking/redocking of a sidebar tab: Done.
- Task (VWR-20970) Implement undocking tabs by dragging: Done.
FUTURE
- Task (VWR-21060) Fix broken ability to open a side tray tab via shortcut, menu item or button outside of the Side Tray.
- Fix recently discovered bugs.
IMPEDIMENTS
- Do we need a new art for "Undock" button in Side Tray. For now I used the existing floater "Tear Off" button.
- Task (VWR-20697) Write code to allow for redocking of a sidebar tab
Anya
OOO
Past Updates
- Thursday, September 2, 2010
- Wednesday, September 1, 2010
- Tuesday, August 31, 2010 - No Daily Scrum, Sprint 2 Retrospective & Sprint 3 Planning Meetings took place
- Monday, August 30, 2010
- Friday, August 27, 2010 - No Daily Scrum, Sprint 2 Review took place
- Thursday, August 26, 2010
- Wednesday, August 25, 2010
- Tuesday, August 24, 2010
- Monday, August 23, 2010
- Friday, August 20, 2010
- Thursday, August 19, 2010
- Wednesday, August 18, 2010
- Tuesday, August 17, 2010 - No Daily Scrum, Sprint 2 Planning took place
- Monday, August 16, 2010