General Notes


  • Sprint 11 Theme - Customization
  • Please do not pick up issues tagged with needs-design until the tag has been removed.
  • MMOTD: Merov
  • Please remember to move issues to current Sprint when a) starting work on them or b) accepting issues from the community
  • Groundhog day!

Team Status


Merov Linden


PAST

  • Meetings, meetings: sprint 11 planning, VWR triaging and OH all in one day...
  • PO build: done
  • Merge Monkeying: cleaned up sprint 10 and previous
  • Triage SNOW JIRA
  • Dig into Coverity findings

FUTURE

  • MM
  • STORM-746 : KDU Improvements: Compress j2c with precincts

IMPEDIMENTS

  • none

Oz Linden


PAST

  • Meetings most of yesterday
  • Other non-Snowstorm activities

FUTURE

  • Try to fix using autobuild with VS Express

IMPEDIMENTS

  • snow, ice, snow, ice....

Q Linden


PAST

  • STORM-465
  • Coverity stuff
  • triage
  • lots of ad hoc meetings
  • snow

FUTURE

  • more snow
  • ooo doctor / pt
  • triage bot

IMPEDIMENTS

  • none

Grumpity ProductEngine


PAST

  • Sprint planning
  • VWR triage
  • Jira wrangling
    • updated needs-design issues
    • closed dupes of issues in current sprint
    • moved issues accepted from community into current sprint

FUTURE

  • PEQA deferred issues triage with Bambers
  • continue to prod others to resolve impediments
    • STORM-379, STORM-465

IMPEDIMENTS

  • moving
  • sick

Paul ProductEngine


PAST

  • BUG STORM-655 (mismatched filter extension in snapshot floater (jpeg vs jpg).)
    • Fixed and sent for review.
  • BUG STORM-680 (Avaline callers are added to the Recent list)
    • WIP. Estimate ~ 6-8 hours.

FUTURE

  • BUG STORM-680 (Avaline callers are added to the Recent list)

IMPEDIMENTS

  • none

Seth Productengine


PAST

  • BUG (STORM-379) Content permissions aren't refreshed in the "Buy copy of" floater.
    • Investigating possible fix with updating "Buy copy of" floater each time it is shown.

FUTURE

  • BUG (STORM-433) Friendship offer shifted up and placed over "Second Life" text

IMPEDIMENTS

  • BUG (STORM-379) Content permissions aren't refreshed in the "Buy copy of" floater.
    • Asked in JIRA whether the bug should be fixed in a way that may increase server load.

Vadim Productengine


PAST

  • STORM-2 (Customizable viewer layouts):
    • Implementing saving sidetray state. ETA: 1d.
  • Sprint planning meeting.

FUTURE

  • Continue with STORM-2.

IMPEDIMENTS

  • STORM-465 (Missing Strings from strings.xml):
    • 
Waiting for Q to provide code-related feedback.

Andrey ProductEngine


PAST

  • picked up 2.5.0 Beta3 r220094 build
  • smoke tests have been passed on Linux, OSX, and Windows, refer to the spreadsheet
  • integrity test has been failed by VWR-24681, but I think this is some kind of a server-side issue
  • 2.5.0 bug-fixes verification almost has been completed, refer to spreadsheet
    • 87 tickets marked as "Deferred" because TPE has no clue how to verify those
  • reported 4 tickets
  • picked up v-d 220024 build
    • verified 3 issues
    • proceeded with regression testing of v-d branch

FUTURE

  • proceed with regression testing of v-d build

IMPEDIMENTS

  • none


Wolfpup Lowenhar


PAST

  • Worked @ RL .
  • STORM-236 : read Oz's comments on JIRA
    • emailed Oz with comments concerning suggestions and what it could entail to get suggested capability in the context menu for the bottom tray and the other issues in the rest of the comment.
  • STORM-941 : Began looking in code for possible places where the issue could be happening.
  • Attended SnowStorm OH which ended up being canceled due to weather in Boston

FUTURE

  • Work @ RL
  • STORM-941 : email Oz and Leyla concerning possible areas that could be causing the problem.

IMPEDIMENTS

  • STORM-236 : waiting for new graphics and name to call the panel.
  • Not enough time to actually work on code.

Jonathan Yap


PAST

  • VWR-24628 (Descriptive text missing next to first checkbox in About Land/Access)
    • This had to be fixed first in order to work on Storm - 953. 4 other people helped with this! This was my proudest moment as a developer. Great team effort. Easy fix but caused by low-level routine change.
  • STORM-953 (Clarify what happens when you uncheck Allow Public Access)

FUTURE

IMPEDIMENTS

  • VWR - 24628 needs to be pulled in to Storm-nnnn
  • Waiting for Oz to Storm-nnnn-ize my bug list.

Cummere Mayo


PAST

  • jira work
  • blog post to lindenwatch

FUTURE

  • office hours
  • jira work
  • working on sl store

IMPEDIMENTS