== Thursday, August 26, 2010 ==
== Monday, August 30, 2010 ==


=== General Notes ===
=== General Notes ===
----
----
* No Daily Scrum tomorrow. Sprint Review Meeting Scheduled from 6-9am PT.  
* No Daily Scrum tomorrow. Sprint Retrospective (6-7am PT) & Sprint Planning Meeting (7-9am PT) will be held instead.




Line 15: Line 15:
====Aimee====
====Aimee====
----
----
<b>PAST</b><br />
UK Bank Holiday
* Reviewed and pulled Merov's llkdu fixes.
* Attended Snowstorm OH.
* Imported and merged double-click teleport patch from Snowglobe.
 
<b>FUTURE</b><br />
* Finish off double-click teleport and get a build up for design review.
* Team meeting.
* Howard's software dev meeting.
* Get back to importing Snowglobe build fixes
* Check with CG about renaming TeamCity projects to Viewer-Release-Builds, and Viewer-Project-Builds so that they sort together in the project list. May also need Viewer-Aimee's-Builds as I seem to be accumulating enough for my own project :)
 
<b>IMPEDIMENTS</b><br />
* None
 


====Tofu====
====Tofu====
----
----
OOO
UK Bank Holiday




Line 39: Line 25:
----
----
<b>PAST</b><br />
<b>PAST</b><br />
* essentially no Snowstorm work yesterday
* Tested, reviewed, and pulled fixes from PE
* Pulled build system improvements from Team Chopper
* Wiki updates


<b>FUTURE</b><br />
<b>FUTURE</b><br />
* update patch from Thickbrick for texture alignment, get it reviewed.
* Office Hour
* get archive of my last Office Hour posted
* Post first Development build on secondlife.com !
* todays Office Hour
* More wiki updates
* Poll open source devs re: next sprint contributions


<b>IMPEDIMENTS</b><br />
<b>IMPEDIMENTS</b><br />
* Non-Snowstorm tasks (no help for it)
* None




Line 53: Line 42:
----
----
<b>PAST</b><br />
<b>PAST</b><br />
* LLKDU in viewer-development: review. Logged VWR-20946 to track this. Got -1 review by Mani: Linux doesn't load llkdu. Aimee to pull the change though so we get Windows at least to build correctly.
* LLKDU in viewer-development: Done!
* Add "Sit" to the "pie" menu: Got everything ready for review and pull. Created a merov-viewer-development-features repo and TeamCity tasks to share, review and test. Q is: how do we move swiftly with the rest of the process?
* Add "Sit" to the "pie" menu: Done!
* Unplanned: lots of discussions on llkdu with lab folks...
* Lots of code review


<b>FUTURE</b><br />
<b>FUTURE</b><br />
* LLKDU in viewer-development: fix the Linux issue.
* LLKDU upgrade: get all info, details, etc... so we can estimate that work
* Add "Sit" to the "pie" menu: Design review (VWR-20711)
* Code review, tests and clean up for sprint 2 as required
* Add "Sit" to the "pie" menu: Test the ability to sit "anywhere" (VWR-20712)
* Look into Snowglobe backlog for next sprint


<b>IMPEDIMENTS</b><br />
<b>IMPEDIMENTS</b><br />
* Need clarity as to how we cover the "review, vet, pull" steps of the process in a swift and efficient way (see http://wiki.secondlife.com/wiki/Viewer_Integration_and_Release_Processes)
* None




==== Q ====
==== Q ====
----
----
<i>OOO</i>
<i>OOO</i> - Getting released from the rehab hospital tomorrow!
 




Line 74: Line 64:
----
----
<b>PAST</b><br />
<b>PAST</b><br />
* Hold first Product Backlog & Idea OH
* Finished Jira EXT triage
* Review texture alignment build for Oz
* Finally started reviewing Resident feedback and ideas for backlog
* Discussion about UI Toolkit
* Discussion about UI customization


<b>FUTURE</b><br />
<b>FUTURE</b><br />
* Get Resident ideas and feedback into the idea tab of backlog
* Prepare for Sprint Planning Meeting tomorrow
* Document idea submission process
* Get Resident ideas and feedback into the backlog
* Review Tofu's list of changes from viewer-public
* Team Meeting
* Howard's 'Quick or Dead' Meeting


<b>IMPEDIMENTS</b><br />
<b>IMPEDIMENTS</b><br />
Line 92: Line 77:
==== Paul ====
==== Paul ====
----
----
<b>PAST</b><br />
OOO - sick
*BUG EXT- 8722 (Appearance > 'Wearing' tab: Add Take off / Detach function to the gear menu)
**In progress 60%.
 
<b>FUTURE</b><br />
*BUG EXT- 8722 (Appearance > 'Wearing' tab: Add Take off / Detach function to the gear menu)
 
<b>IMPEDIMENTS</b><br />
*none




Line 107: Line 84:
<b>PAST</b><br />
<b>PAST</b><br />
*Task VWR-20702 (Snowstorm Sprint 2: As a User who's customized the bottom bar of the Viewer UI, I also want to be able to control the order of the buttons as they appear in the UI.)
*Task VWR-20702 (Snowstorm Sprint 2: As a User who's customized the bottom bar of the Viewer UI, I also want to be able to control the order of the buttons as they appear in the UI.)
**WIP. Working on D&D similar to favorites, will finish tomorrow.  
** Found servious problems with D&D implementation, leading to crashes.  Will not be able to complete in this sprint. May need to consider a different implementation for reordering.  


<b>FUTURE</b><br />
<b>FUTURE</b><br />
*Task VWR-20702  
*Task VWR-20702  
**analyze d&d in favorites, add similar to bottom tray
**change order of buttons shrinking and disappearing depending on button locations
**save order in settings and use it when creating bottom tray
**investigate inconsistency in distance between buttons


<b>IMPEDIMENTS</b><br />
<b>IMPEDIMENTS</b><br />
* Order of buttons shrinking and disappearing
* D&D implementation.  Will ask for LL consult tomorrow.




Line 123: Line 96:
----
----
<b>PAST</b><br />
<b>PAST</b><br />
*Task VWR-20964 (Enable sidebar to track detaching/attaching tabs):
*Fixed small bug in Detachable tabs
**70% complete.
*Got a bitbucket account and cloned viewer-development there


<b>FUTURE</b><br />
<b>FUTURE</b><br />
*create repo to work on detachable tabs, add my code for VWR-20964, integarte with Sergey's code.  
*Various fixes and polish for Detachable tabs.
*figure out how else to help Sergey


<b>IMPEDIMENTS</b><br />
<b>IMPEDIMENTS</b><br />
*none
* Should we create separate tasks for these fixes & polish? Where and how should they be committed?




Line 138: Line 110:
<b>PAST</b><br />
<b>PAST</b><br />
*Task (VWR-20696) Write code to allow for undocking of a sidebar tab
*Task (VWR-20696) Write code to allow for undocking of a sidebar tab
*Task (VWR-20697) Write code to allow for redocking of a sidebar tab
**Fixed.
**Fixed undocked tab visibility changes when switching tabs in Side Tray.
* Task (VWR-20697) Write code to allow for redocking of a sidebar tab
**Added undocking multiple tabs from Side Tray.
**Fixed.
**Fixed Side Tray expanding/collapsing on undocking/undocking tabs.
**Fixed selecting re-docked tab and toggling its tag button state.
**Minor optimization of Side Tray expanding/collapsing upon toggling tab docked/undocked.
*Task (VWR-20970) Implement undocking tabs by dragging.
**WIP.


<b>FUTURE</b><br />
<b>FUTURE</b><br />
* Task (VWR-20696) Write code to allow for undocking of a sidebar tab
* Task (VWR-20970) Implement undocking tabs by dragging. Estimated: 4-5 hours.
* Task (VWR-20697) Write code to allow for redocking of a sidebar tab
* Integrate with Vadim's code to complete both tasks tomorrow no significant bugs are found


<b>IMPEDIMENTS</b>
<b>IMPEDIMENTS</b><br />
*need design soon
*none




Line 155: Line 128:
----
----
<b>PAST</b><br />
<b>PAST</b><br />
*GH & new jira demo
* Discuss next sprint process
*Followup on future workflow and PE process
* Finalize design for bottom bar reordring VWR-20706
*Played with new jira
*Investigated platform testing status
*maintenance/org


<b>FUTURE</b><br />
<b>FUTURE</b><br />
*VWR-20702 design - button shrinking/disappearing - follow up with Ben
* Follow up design discussion in VWR-20695
*esablish procedure for taking EXTs from old PE backlog to particular sprint
* Find and torture Lindens who can help sort out some issues with VWR-20702
* Clean up Jira (remove devs no longer here, change assignments, talk to QA who assign to devs that are gone)


<b>IMPEDIMENTS</b><br />
<b>IMPEDIMENTS</b><br />
*out thu-fri next week
*we're not making VWR-20702 in this sprint. it was underestimated due to unexpected D&D implementation problems (all D&D behavior is currently tied to inventory. 
 





Revision as of 08:33, 30 August 2010


Monday, August 30, 2010

General Notes


  • No Daily Scrum tomorrow. Sprint Retrospective (6-7am PT) & Sprint Planning Meeting (7-9am PT) will be held instead.


Team Status


Aimee


UK Bank Holiday

Tofu


UK Bank Holiday


Oz


PAST

  • Tested, reviewed, and pulled fixes from PE
  • Pulled build system improvements from Team Chopper
  • Wiki updates

FUTURE

  • Office Hour
  • Post first Development build on secondlife.com !
  • More wiki updates
  • Poll open source devs re: next sprint contributions

IMPEDIMENTS

  • None


Merov


PAST

  • LLKDU in viewer-development: Done!
  • Add "Sit" to the "pie" menu: Done!
  • Lots of code review

FUTURE

  • LLKDU upgrade: get all info, details, etc... so we can estimate that work
  • Code review, tests and clean up for sprint 2 as required
  • Look into Snowglobe backlog for next sprint

IMPEDIMENTS

  • None


Q


OOO - Getting released from the rehab hospital tomorrow!


Esbee


PAST

  • Finished Jira EXT triage
  • Finally started reviewing Resident feedback and ideas for backlog

FUTURE

  • Prepare for Sprint Planning Meeting tomorrow
  • Get Resident ideas and feedback into the backlog

IMPEDIMENTS

  • None


Paul


OOO - sick


Andrew


PAST

  • Task VWR-20702 (Snowstorm Sprint 2: As a User who's customized the bottom bar of the Viewer UI, I also want to be able to control the order of the buttons as they appear in the UI.)
    • Found servious problems with D&D implementation, leading to crashes. Will not be able to complete in this sprint. May need to consider a different implementation for reordering.

FUTURE

  • Task VWR-20702

IMPEDIMENTS

  • D&D implementation. Will ask for LL consult tomorrow.


Vadim


PAST

  • Fixed small bug in Detachable tabs
  • Got a bitbucket account and cloned viewer-development there

FUTURE

  • Various fixes and polish for Detachable tabs.

IMPEDIMENTS

  • Should we create separate tasks for these fixes & polish? Where and how should they be committed?


Sergey


PAST

  • Task (VWR-20696) Write code to allow for undocking of a sidebar tab
    • Fixed.
  • Task (VWR-20697) Write code to allow for redocking of a sidebar tab
    • Fixed.
    • Fixed selecting re-docked tab and toggling its tag button state.
    • Minor optimization of Side Tray expanding/collapsing upon toggling tab docked/undocked.
  • Task (VWR-20970) Implement undocking tabs by dragging.
    • WIP.

FUTURE

  • Task (VWR-20970) Implement undocking tabs by dragging. Estimated: 4-5 hours.

IMPEDIMENTS

  • none


Anya


PAST

  • Discuss next sprint process
  • Finalize design for bottom bar reordring VWR-20706

FUTURE

  • Follow up design discussion in VWR-20695
  • Find and torture Lindens who can help sort out some issues with VWR-20702
  • Clean up Jira (remove devs no longer here, change assignments, talk to QA who assign to devs that are gone)

IMPEDIMENTS

  • we're not making VWR-20702 in this sprint. it was underestimated due to unexpected D&D implementation problems (all D&D behavior is currently tied to inventory.


Past Updates