| == Monday, August 30, 2010 == | | == Tuesday, August 31, 2010 == |
|
| |
|
| === General Notes === | | === General Notes === |
| ---- | | ---- |
| * No Daily Scrum tomorrow. Sprint Retrospective (6-7am PT) & Sprint Planning Meeting (7-9am PT) will be held instead. | | * No Daily Scrum today. Sprint Retrospective (6-7am PT) & Sprint Planning Meeting (7-9am PT) will be held instead. |
| | |
| | |
| ===Team Status===
| |
| ----
| |
| | |
| ====Aimee====
| |
| ----
| |
| UK Bank Holiday
| |
| | |
| ====Tofu====
| |
| ----
| |
| UK Bank Holiday
| |
| | |
| | |
| ====Oz====
| |
| ----
| |
| <b>PAST</b><br />
| |
| * Tested, reviewed, and pulled fixes from PE
| |
| * Pulled build system improvements from Team Chopper
| |
| * Wiki updates
| |
| | |
| <b>FUTURE</b><br />
| |
| * Office Hour
| |
| * Post first Development build on secondlife.com !
| |
| * More wiki updates
| |
| * Poll open source devs re: next sprint contributions
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| * None
| |
| | |
| | |
| ==== Merov ====
| |
| ----
| |
| <b>PAST</b><br />
| |
| * LLKDU in viewer-development: Done!
| |
| * Add "Sit" to the "pie" menu: Done!
| |
| * Lots of code review
| |
| | |
| <b>FUTURE</b><br />
| |
| * LLKDU upgrade: get all info, details, etc... so we can estimate that work
| |
| * Code review, tests and clean up for sprint 2 as required
| |
| * Look into Snowglobe backlog for next sprint
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| * None
| |
| | |
| | |
| ==== Q ====
| |
| ----
| |
| <i>OOO</i> - Getting released from the rehab hospital tomorrow!
| |
| | |
| | |
| | |
| ==== Esbee ====
| |
| ----
| |
| <b>PAST</b><br />
| |
| * Finished Jira EXT triage
| |
| * Finally started reviewing Resident feedback and ideas for backlog
| |
| | |
| <b>FUTURE</b><br />
| |
| * Prepare for Sprint Planning Meeting tomorrow
| |
| * Get Resident ideas and feedback into the backlog
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| * None
| |
| | |
| | |
| ==== Paul ====
| |
| ----
| |
| OOO - sick
| |
| | |
| | |
| ==== Andrew ====
| |
| ----
| |
| <b>PAST</b><br />
| |
| *Task VWR-20702 (Snowstorm Sprint 2: As a User who's customized the bottom bar of the Viewer UI, I also want to be able to control the order of the buttons as they appear in the UI.)
| |
| ** Found servious problems with D&D implementation, leading to crashes. Will not be able to complete in this sprint. May need to consider a different implementation for reordering.
| |
| | |
| <b>FUTURE</b><br />
| |
| *Task VWR-20702
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| * D&D implementation. Will ask for LL consult tomorrow.
| |
| | |
| | |
| ==== Vadim ====
| |
| ----
| |
| <b>PAST</b><br />
| |
| *Fixed small bug in Detachable tabs
| |
| *Got a bitbucket account and cloned viewer-development there
| |
| | |
| <b>FUTURE</b><br />
| |
| *Various fixes and polish for Detachable tabs.
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| * Should we create separate tasks for these fixes & polish? Where and how should they be committed?
| |
| | |
| | |
| ==== Sergey ====
| |
| ----
| |
| <b>PAST</b><br />
| |
| *Task (VWR-20696) Write code to allow for undocking of a sidebar tab
| |
| **Fixed.
| |
| * Task (VWR-20697) Write code to allow for redocking of a sidebar tab
| |
| **Fixed.
| |
| **Fixed selecting re-docked tab and toggling its tag button state.
| |
| **Minor optimization of Side Tray expanding/collapsing upon toggling tab docked/undocked.
| |
| *Task (VWR-20970) Implement undocking tabs by dragging.
| |
| **WIP.
| |
| | |
| <b>FUTURE</b><br />
| |
| * Task (VWR-20970) Implement undocking tabs by dragging. Estimated: 4-5 hours.
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| *none
| |
| | |
| | |
| ==== Anya ====
| |
| ----
| |
| <b>PAST</b><br />
| |
| * Discuss next sprint process
| |
| * Finalize design for bottom bar reordring VWR-20706
| |
| | |
| <b>FUTURE</b><br />
| |
| * Follow up design discussion in VWR-20695
| |
| * Find and torture Lindens who can help sort out some issues with VWR-20702
| |
| * Clean up Jira (remove devs no longer here, change assignments, talk to QA who assign to devs that are gone)
| |
| | |
| <b>IMPEDIMENTS</b><br />
| |
| *we're not making VWR-20702 in this sprint. it was underestimated due to unexpected D&D implementation problems (all D&D behavior is currently tied to inventory.
| |
| | |
|
| |
|
|
| |
|