Snowstorm Daily Scrum Archive

From Second Life Wiki
Revision as of 08:33, 30 August 2010 by Esbee Linden (talk | contribs)
Jump to navigation Jump to search


Monday, August 30, 2010

General Notes


  • No Daily Scrum tomorrow. Sprint Retrospective (6-7am PT) & Sprint Planning Meeting (7-9am PT) will be held instead.


Team Status


Aimee


UK Bank Holiday

Tofu


UK Bank Holiday


Oz


PAST

  • Tested, reviewed, and pulled fixes from PE
  • Pulled build system improvements from Team Chopper
  • Wiki updates

FUTURE

  • Office Hour
  • Post first Development build on secondlife.com !
  • More wiki updates
  • Poll open source devs re: next sprint contributions

IMPEDIMENTS

  • None


Merov


PAST

  • LLKDU in viewer-development: Done!
  • Add "Sit" to the "pie" menu: Done!
  • Lots of code review

FUTURE

  • LLKDU upgrade: get all info, details, etc... so we can estimate that work
  • Code review, tests and clean up for sprint 2 as required
  • Look into Snowglobe backlog for next sprint

IMPEDIMENTS

  • None


Q


OOO - Getting released from the rehab hospital tomorrow!


Esbee


PAST

  • Finished Jira EXT triage
  • Finally started reviewing Resident feedback and ideas for backlog

FUTURE

  • Prepare for Sprint Planning Meeting tomorrow
  • Get Resident ideas and feedback into the backlog

IMPEDIMENTS

  • None


Paul


OOO - sick


Andrew


PAST

  • Task VWR-20702 (Snowstorm Sprint 2: As a User who's customized the bottom bar of the Viewer UI, I also want to be able to control the order of the buttons as they appear in the UI.)
    • Found servious problems with D&D implementation, leading to crashes. Will not be able to complete in this sprint. May need to consider a different implementation for reordering.

FUTURE

  • Task VWR-20702

IMPEDIMENTS

  • D&D implementation. Will ask for LL consult tomorrow.


Vadim


PAST

  • Fixed small bug in Detachable tabs
  • Got a bitbucket account and cloned viewer-development there

FUTURE

  • Various fixes and polish for Detachable tabs.

IMPEDIMENTS

  • Should we create separate tasks for these fixes & polish? Where and how should they be committed?


Sergey


PAST

  • Task (VWR-20696) Write code to allow for undocking of a sidebar tab
    • Fixed.
  • Task (VWR-20697) Write code to allow for redocking of a sidebar tab
    • Fixed.
    • Fixed selecting re-docked tab and toggling its tag button state.
    • Minor optimization of Side Tray expanding/collapsing upon toggling tab docked/undocked.
  • Task (VWR-20970) Implement undocking tabs by dragging.
    • WIP.

FUTURE

  • Task (VWR-20970) Implement undocking tabs by dragging. Estimated: 4-5 hours.

IMPEDIMENTS

  • none


Anya


PAST

  • Discuss next sprint process
  • Finalize design for bottom bar reordring VWR-20706

FUTURE

  • Follow up design discussion in VWR-20695
  • Find and torture Lindens who can help sort out some issues with VWR-20702
  • Clean up Jira (remove devs no longer here, change assignments, talk to QA who assign to devs that are gone)

IMPEDIMENTS

  • we're not making VWR-20702 in this sprint. it was underestimated due to unexpected D&D implementation problems (all D&D behavior is currently tied to inventory.