Snowstorm Daily Scrum Archive
Project Snowstorm Daily Scrum Archive
Friday, August 20, 2010
General Notes
- Q OOO until further notice
- Don't forget to update the time you spent on a task in the Sprint Backlog at the end of each day!
Team Status
Aimee
PAST
- Staged some more build fixes from Snowglobe into aimee_linden/viewer-development-import
- Merged into to viewer-development
- More Mercurial and bitbucket guidance to open source contributors
- Helped Oz get SSH to Bitbucket going
FUTURE
- Pull in some more Snowglobe fixes
- Merge from aimee_linden/viewer-development-import to viewer-development
- Find out what we're doing about stuff in viewer-public and viewer-release? Merge / convert / merge?
IMPEDIMENTS
- None.
Tofu
OOO
Oz
PAST
- Fixed ssh authentication problem (thanks Aimee)
- Process discussions
- Got deeper training on TeamCity
- Discussions with tools team on common code issues
- Set up new canonical build for viewer-development (changed 'oz' to 'snowstorm' in name).
- Set up experimental repository & build
- Code review of submission from WolfPup (building now)
FUTURE
- More wiki improvements
- Post archive of Wednesdays OH
- Add transcriber to this scrum meeting space
IMPEDIMENTS
- none
Merov
PAST
- LLKDU in viewer-development: Analyzed the llkdu.dll crash on Windows on launch. Aimee was right : we will have to port all of SNOW-345 (see http://jira.secondlife.com/browse/SNOW-345) fixes to Snowstorm. The good news is I know what to do now. The bad news is that last time I did it consumed 3 days to get things right. I'm thinking of ways to just tease the lib without rebuilding it and point install.xml to it.
- Got all my bitbucket and TeamCity ducks in a row: there's now a merov_linden/viewer-development-import repo (same model as Aimee's)
- Snowglobe: completed cleanup of 1.x (SNOW-713 issues)
FUTURE
- LLKDU in viewer-development: Try the fixed llkdu.dll from Snowglobe 1.4 bluntly as a test
- LLKDU in viewer-development: Move the relevant SNOW-345 changes to Snowstorm
- LLKDU in viewer-development: Modify build.sh to download the llkdu libs even when -DINSTALL_PROPRIETARY:BOOL=ON is not set
- LLKDU in viewer-development: Create a separate private repo for building llkdu cleaning from code (need to double check that with brad)
IMPEDIMENTS
- None
Q
OOO
Esbee
PAST
- Triaging EXT bugs and prepping to convert them to VWR
- Continued response to blog and SLCC feedback
- Discussion with QA about integration and release process
- Started sketch of undockable sidebar tabs
FUTURE
- Finish sketch undockable/dockable sidebar design and send to XD team for a quick review
- Set up weekly office hours to discuss product backlog and ideas!
- Continue Jira triage
- Continue to follow up on SLCC and Snowstorm blog feedback
- Start adding Resident feedback/ideas/user stories to the Snowstorm Backlog on a new tab
- Document idea submission process and worm with those ideas
- Flying back to SF on Sunday
IMPEDIMENTS
- None
Paul
PAST
- BUG EXT-8405 (Clicking an attachment switches the Add More inventory to Flat view)
- In progress 95%.
FUTURE
- BUG EXT-8405 (Clicking an attachment switches the Add More inventory to Flat view)
IMPEDIMENTS
- none
- note: vacation request 09.13-09.24
Andrew
PAST
- Pushed tickets that passed review
- Task VWR-20703(Research bottom bar code)
- Investigation more or less complete
- Started writing test code for moving buttons
- Cloned and built viewer-development
FUTURE
- Task VWR-20702(Snowstorm Sprint 2: As a User who's customized the bottom bar of the Viewer UI, I also want to be able to control the
order of the buttons as they appear in the UI.)
IMPEDIMENTS
- none
Vadim
PAST
- Task VWR-20724 (Missing underlined shortcuts in some top-level menus):
- Implemented, committed.
- Task VWR-20734 (Changed parcel properties to default to "on" in the location bar):
- Implemented, committed.
- Helping web site developers to investigate a problem with viewer requiring user to upgrade to Premium account before buying a parcel on the mainland.
FUTURE
- Discuss proposed commit process
- Proceed with Sprint #2 tasks.
IMPEDIMENTS
- What to do with tickets we no longer work on? How to pass them to QA ?
Sergey
PAST
- Bug (EXT-7325) My Landmarks: "Show on Map" context menu item is enabled while "Map" button is disabled for selected landmark.
- Pushed fix.
- Bug (EXT-8697) My Landmarks: 'Cut' item should be greyed out in folder's context menu
- Pushed fix.
- Bug (VWR-20694) Snowstorm Sprint 2: As a User, I want to undock tabs from the Viewer sidebar so that I can control what tabs are displayed and organize them on my screen in any way I want like I could do in 1.23.
- WIP. Researching Side Bar, Dockable Floater code.
FUTURE
- Bug (VWR-20694) Snowstorm Sprint 2: As a User, I want to undock tabs from the Viewer sidebar so that I can control what tabs are displayed and organize them on my screen in any way I want like I could do in 1.23.
IMPEDIMENTS
- none
- Vacation Sept 6-9
Anya
PAST
- Investigation/Discussion of suggested new commit process for PE
- Clarified tasks/bugs
- Discussed with Bambers options for Snowstorm QA
FUTURE
- figure out process for Hg
- discuss QA options with Esbee & Bambers
- get answers to questions listed as impediments
- crashhunters
IMPEDIMENTS
- No tasks to take from backlog that don't require design
- Should I add EXT bugs we're currently working on to the sprint backlog? (20%)
- How best to engage QA in the Snowstorm process?
- Vadim: How to assign/pass issues to QA?
- Task EXT-7756 (Add sort order to My Outfits gear menu (name or date)) - how to deal with server changes?
Past Updates
- Monday, August 16, 2010
- Tuesday, August 17, 2010 - No Daily Scrum today, Sprint 2 Planning took place
- Wednesday, August 18, 2010
- Thursday, August 19, 2010