Snowstorm Daily Scrum Archive

From Second Life Wiki
Jump to navigation Jump to search


Sprint 15, ends 05.16.11

Tuesday, April 26

General Notes


  • Sprint 15 will be 3 weeks to partially compensate for holidays and vacations
  • Seth vacation this week
  • Oz vacation Wed-Fri.

Team Status


Oz Linden


PAST

  • Sprint Planning
  • Contributor build farm work
  • Assorted internal reviews

FUTURE

  • More GPU table updates (STORM-1100)

IMPEDIMENTS

  • 4 days in Las Vegas

Wolf Linden


PAST

  • Storm-2
    • sketched out workflow
    • preliminary wireframes
    • compiled list of all windows and associated functionality

FUTURE

  • Wireframes
  • more work on windows

IMPEDIMENTS

  • none

Grumpity ProductEngine


PAST

  • sprint planning
  • triage
  • jira cleanup

FUTURE

  • triage
  • crashhunters
  • meetings

IMPEDIMENTS

  • reopened issues keep value for approvals.

Paul ProductEngine


PAST

  • BUG STORM-951 (Accidental Self-Muting/Self-Blocking)
    • Fixed. After meeting will send for review.
    • While I was working on STORM-951 I was faced with problem which I wanted to solve within STORM-951. But it seems that it's not very trivial. It's not directly related to the STORM-951 so I will create JIRA issue for it after meeting.

FUTURE

  • Work on Windlight Region Settings.

IMPEDIMENTS

  • none

Vadim ProductEngine


PAST

  • Investigated new WLRS spec and provided my feedback.
  • Working on defining WLRS implementation tasks.

FUTURE

  • Finish defining WLRS tasks.
  • Start implementing them.

IMPEDIMENTS

  • none

Andrey ProductEngine


PAST

  • passed smoke & integrity tests for 2.6.3 RC r227447, see IQA-152 for more details
  • passed testing in scope of STORM-1028 on oz_viewer-poreview build
  • tested v-d integrated issues on the latest v-d build
    • 7 passed QA and 2 reopened

FUTURE

  • pickup 2.6.6 beta build

IMPEDIMENTS

  • none

Wolfpup Lowenhar


PAST

  • Working inworld (this is part of testing localy built viewers).
    • Checking on horses and bundles, plus work on note cards for them.
    • Desiding on what type of build to work on next.
  • OPEN-9 : still TBD.
    • This is marked ready for review.

FUTURE

  • Working inworld(this is part of testing localy built viewers).
  • STORM-1182 : create local repository for investigation for Windows since Linux and Mac have already been done.

IMPEDIMENTS

  • Getting Autobuild system and seceurity software to play nicely on my system.
  • Intermittent power issues with system (looks like will be having to replace the power supply).

Past Updates

Aprli
25 | 14 | 13 | 12 | 07 | 06

March
31 | 30 | 29 | 19 | 18 | 17 | 16 | 15 | 14 | 11 | 10 | 09 | 08 | 07 | 04 | 03 | 02 | 01

February
28 | 25 | 24 | 23 | 22 | 18 | 16 | 15 | 14 | 11 | 10 | 09 | 08 | 07 | 04 | 03 | 02 | 01 |

January
31 | 28 | 27 | 26 | 25 | 24 | 21 | 20 | 19 | 18 | 14 | 13 | 12 | 11 | 10 | 06 | 06 | 05 | 04

2010
December
30 | 23 | 22 | 21 | 20 | 17 | 16 | 15 | 14 | 13 | 10 | 09 | 08 | 07 | 06 | 03 | 02 | 01

November
30 | 29 | 24 | 23 | 22 | 19 | 18 | 17 | 16 | 15 | 12 | 11 | 10 | 09 | 08 | 05 | 04 | 03 | 02 | 01

October
29 | 28 | 27 | 26 | 25 | 22 | 21 | 20 | 18 | 15 | 14 | 13 | 12 | 11 | 08 | 07 | 06 | 05 | 04 | 01

September
27 | 24 | 21 | 20 | 17 | 16 | 15 | 14 | 13 | 09 | 08 | 07 | 03 | 02 | 01

August
30 | 26 | 25 | 24 | 23 | 20 | 19 | 18 | 16