Sprint 15, ends 05.16.11

Thursday, May 5

Team Status


Oz Linden


PAST

  • More trial merges of mesh (not yet in viewer-development)
  • Planning contributor build system deployment
  • VWR Triage
  • Open Development User Group

FUTURE

  • Rewrite GPU table regression test (STORM-1100) in python
  • Windlight Project viewer build
  • Windlight spec review
  • Code reviews

IMPEDIMENTS

  • none

Wolf Linden


PAST

  • WLRS p. 23 follow up with Oz,
  • updated pg. 8,
  • finalized first draft of specs for customizable UI;
  • window UI work

FUTURE

  • More window UI work (making sure I've compiled list of all floaters, etc. and how they work);
  • publishing WLRS specs if there are no more comments

IMPEDIMENTS

  • none

Grumpity ProductEngine


PAST

  • I10n new issues - prioritize, future process
  • WLRS
  • VWR triage

FUTURE

  • STORM-280 (uninstalling) - sort all related issues, close dupes, coordinate with chopper
  • storm triage
  • QA roundup

IMPEDIMENTS

  • none

Paul ProductEngine


PAST

  • BUG STORM-1227 ([crashhunters] crash at LLDir_Win32::getNextFileInDir(std::basic_string,std::allocator > const &,std::basic_string,std::allocator > const &,std::basic_string,std::allocator > &) [secondlife-bin lldir_win32.cpp])
    • Tried to reproduce but had no luck.
  • TASK STORM-1202 ( TASK STORM-1202 (Time spin control))
    • WIP. Estimate ~10 hours.

FUTURE

  • TASK STORM-1202 ( TASK STORM-1202 (Time spin control))

IMPEDIMENTS

  • none

Andrey ProductEngine


PAST

  • picked up 2.6.6 beta build#2 r288224
    • smoke & integrity tests have been failed by two major tickets: VWR-25687, and EXP-749
    • also EXP-755 is reproducible, and VWR-25688 has been reported
  • verified EXP-752
  • continued with regression pass using 2.6.6 beta build
  • tested STORM-1093 changes on the PO build mentioned in the ticket

FUTURE

  • continue v-d testing

IMPEDIMENTS

  • none

Wolfpup Lowenhar


PAST

  • Installed new Power Supply in Windows system and tested.
  • STORM-1100 : Per Oz's instruction in IRC added comment with specification of video card on my Linux laptop.
  • Set up development environment on Lunix notebook computer for basic work.
    • have one issue that is just a warning due to different compiler version between me and LL.

FUTURE

  • STORM-1215: will generate build logs for Oz when windows system is back up and running.

IMPEDIMENTS

  • Getting Autobuild system and security software to play nicely on my system.
  • Weather, as it is storming here and causing power to intermittently go out and do not want to risk damaging new P/S.

Other notes


  • Cron Stardust has been (slowly) working on a change that reverses the gridlines UI, but it's only 50% done in about 2 months... Too many other interruptions in RL life.. :P (And no, I've not created a JIRA for the suggestion...)
  • Jonathan -> Wolf. Q: Storm-1068 decision. A: maps not yet a priority due to basic mode developments
  • audio problem fixed


Past Updates

May
04

April
27 | 26 | 25 | 14 | 13 | 12 | 07 | 06

March
31 | 30 | 29 | 19 | 18 | 17 | 16 | 15 | 14 | 11 | 10 | 09 | 08 | 07 | 04 | 03 | 02 | 01

February
28 | 25 | 24 | 23 | 22 | 18 | 16 | 15 | 14 | 11 | 10 | 09 | 08 | 07 | 04 | 03 | 02 | 01 |

January
31 | 28 | 27 | 26 | 25 | 24 | 21 | 20 | 19 | 18 | 14 | 13 | 12 | 11 | 10 | 06 | 06 | 05 | 04

2010
December
30 | 23 | 22 | 21 | 20 | 17 | 16 | 15 | 14 | 13 | 10 | 09 | 08 | 07 | 06 | 03 | 02 | 01

November
30 | 29 | 24 | 23 | 22 | 19 | 18 | 17 | 16 | 15 | 12 | 11 | 10 | 09 | 08 | 05 | 04 | 03 | 02 | 01

October
29 | 28 | 27 | 26 | 25 | 22 | 21 | 20 | 18 | 15 | 14 | 13 | 12 | 11 | 08 | 07 | 06 | 05 | 04 | 01

September
27 | 24 | 21 | 20 | 17 | 16 | 15 | 14 | 13 | 09 | 08 | 07 | 03 | 02 | 01

August
30 | 26 | 25 | 24 | 23 | 20 | 19 | 18 | 16